Red Cedar announced their efforts underway to build a second phase to their recently completed worship facility.  The plan is to double their current worship space to 1000 seats, add more children’s education capacity and add an indoor playground adjacent to the Café.

Mantel Teter of Kansas City, MO has been retained as the project architect and Northwest Builders of Rice Lake has been selected as the general contractor.  Western Project Management will continue to provide owner’s representative services.  It is great to see this vibrant church continue to grow.

Work is progressing well on the new worship facility.  Structural steel erection is underway and the building volume is beginning to take shape.  Roers Construction and their subcontractors are managing efforts in the Fargo winter.

Big Elk Meadows, CO

Tank Connections completed the installation of the new water storage tank this week. The weather didn’t cooperate but the crew persisted.  The completion of this work is a major milestone and one of the final pieces needed for the overall completion of Big Elk’s revamped water distribution system.

Big Elk Meadows, CO

The Mirror Lake Dam construction is complete and we have received informal approval from the State.  The final certification will occur once all final closeout documentation has been submitted and reviewed by the State of Colorado.

The completion of this first dam was a large step forward for the rebuilding of the Meadows from the devastation left behind in the 2013 floods.